According to city staff, there will be no water flushing today and next week’s proposed schedule for the water flush project looks like this:
On Monday, April 18th, crews will start and most likely finish, the two far-right sections, south of Thornton Street and east of Vista Drive, as shown on Map A (above) in a single day.
On Tuesday, if needed crews will be finishing up the remaining sections from Monday and begin work on areas on Map B (below) starting with the far-left section (blue) and possibly beginning on the second section between Church Road and Hendrickson Avenue before the end of day.
On Wednesday, there will be no water flush happening.
On Thursday, crews will resume work on the second section and most likely finish it that day.
On Friday, there will be no water flush happening.